Erection, Testing & Commissioning of High voltage Equipment’s 6.6kV to 400kV Substation
Major Equipment’s:-

5MVA to 200MVA Power Transformers

VCB & SF6 Circuit Breaker 11kV to 400kV

Capacitive Voltage Transformer 11kV to 400kV

Current Transformers 11kV to 400kV

Lighting Arrestor 11kV to 400kV

Isolators 11kV to 400kV

LT, HT & EHV Cables (Grade 1.1KV to 400kV)
5MVA to 200MVA Power Transformers
- Tan-Delta Test of Bushing.
- Turret CT Testing.
- Ratio of Turret CT.
- Polarity of Turret CT.
- Winding resistance of Turret CT.
- Insulation Resistance Test of Turret CT & core frame.
- Sweep Frequency Response Analyzer (SFRA)Test.
- Tan-Delta Test of Bushing & Winding.
- Magnetic Core Balance Test.
- Magnetic Current Test.
- Short Circuit Impedance Test.
- Vector Group Test.
- Winding Resistance Measurement (WRM) Test.
- Voltage Ratio Test.
- Insulation resistance & Polarization Index Test.
VCB & SF6 Circuit Breaker 11kV to 765kV
- DCRM (Dynamic Contact resistance measurement)
- Timing Test.
- Contact Resistance measurement.
- Insulation Resistance Test.
Capacitive Voltage Transformer 11kV to 765kV
- Tan- Delta Test.
- Ratio Test.
- Polarity Test.
- Continuity Test.
- Winding resistance Test.
- Insulation Resistance Test.
Current Transformers 11kV to 765kV
- Tan- Delta Test. Ratio Test.
- Polarity Test. Continuity Test.
- Winding resistance Test.
- Insulation Resistance Test.
Potential Transformer
- Ratio Test.
- Polarity Test.
- Continuity Test.
- Winding resistance Test.
- Insulation Resistance Test.
Lighting Arrestor 11kV to 765kV
- Tan- Delta Test.
- LeakageCurrent Measurement.
- Insulation Resistance Test.
Isolators 11kV to 765kV
- Contact Resistance Measurement.
- Insulation Resistance Test.
33Kv HT Panels
- Ratio Test of CT & PT.
- Polarity Test.
- Continuity Test.
- Winding resistance Test.
- Timing Test of CB.
- Contact Resistance measurement CB.
- Insulation Resistance Test.
- Relay Configuration checks.
LT, HT & EHV Cables (Grade 1.1KV to 400kV)
- Hi-Pot Test.
- VLF Test.
- Partial Discharge Test.
- Insulation Resistance Test.
Testing & Commissioning of Substation- Up to 765kV
-
Visual Inspection: Verify that all equipment (transformers, circuit breakers, busbars, disconnect switches, etc.) is properly installed.
-
Physical Inspection: Check grounding systems, cable trays, and busbar supports.